PSC ruling is last hurdle Rothschild biomass plant must face

From an article by Kathleen Footy in the Wausau Daily Herald:

ROTHSCHILD — The Wisconsin Department of Natural Resources’ approval Monday of a proposed biomass energy plant leaves just one obstacle in the way of the $250 million project.

The state’s Public Service Commission, including new Chairman Phil Montgomery, is a three-member panel charged with regulating the state’s utilities and vetting new construction projects. The PSC will rule on whether the power plant — a joint project of Milwaukee utility We Energies and Domtar Paper — would serve customers and residents well.

PSC regulators can schedule a meeting on the proposal at any time. The commissioners typically discuss cases at an open meeting in Madison, then finalize an order to be voted on at their next meeting.

Opponents of the Rothschild project, who feel out of options since comments to the PSC are closed, plan to push for the DNR to create a safeguard against emissions from the plant.

Rob Hughes, a member of the citizens group Saving Our Air Resources, or SOAR, said he was disappointed by the DNR’s decision. Hughes said the DNR should move its air-quality monitoring station in Marathon County from Lake DuBay to Rothschild to guarantee residents’ safety.

“It shouldn’t be a big deal since they say the air will be safe,” Hughes said. “That would reassure the community that ‘Yes, the air is safe.’ I think that’s the best we can hope for.”

Wind turbine blade plant on hold

From an article by Nathaniel Shuda in the Wisconsin Rapids Tribune:

Wisconsin Rapids is ready to buy back land it sold to a local company that two years ago announced plans to build a wind-turbine blade manufacturing plant on the property.

Energy Composites Corp. faces a Friday deadline to either reach an agreement with Wisconsin Rapids or sell the nearly 94 acres of land back to the city at the original purchasing price, Mayor Mary Jo Carson said.

Carson said the sale doesn’t necessarily mean the project is dead, but it won’t happen right now.

“Obviously, ECC doesn’t want to hold us up in reference to that land, which we thank them for,” she said. “We appreciate their interest in their hometown.”

Carson said City Attorney Sue Schill has been working with the company’s attorney to reach a buy-back agreement.

On March 31, 2009, the company announced plans to build a 350,000-square-foot plant in the Rapids East Commerce Center that would create at least 400 local jobs. Since then, those plans expanded to 535,000 square feet and more than 600 positions.

To facilitate the project, the city later sold the Wisconsin Rapids-based company 93.7 acres of land in the Rapids East Commerce Center for $500 an acre — a 90 percent discount from the typical asking price — plus a $1,000 option fee, for a total price of $47,850.

Under the pending agreement, the city would buy back the land at the same price for which it sold it, Carson said.

Another wind developer suspends work in Wisconsin

Immediate release:
March 30, 2011

Contact:
Bill French
Midwest Wind Energy
(847) 414-0134
French@midwestwind.com

Midwest Wind suspends project development in Wisconsin

In view of continued regulatory uncertainty in the State of Wisconsin, a leading wind farm developer has announced that it has suspended development activity until a more predictable climate is restored. Chicago-based Midwest Wind Energy, LLC (MWE) has been developing utility scale wind farms in Wisconsin since 2003 and has two of its developed projects operating; one a 54-megawatt project in Dodge County and the other a 67-megawatt project in Fond du Lac County. MWE is also developing a 98-megawatt project in Calumet County and another project which had not yet been announced publicly.

According to MWE President, Stefan Noe, it no longer makes sense to invest significant development capital in a state that appears to be closed to the wind energy business. “Most states are clearly open for renewable energy development and the economic development dollars and jobs that come with it. So long as there are states rolling out the welcome mat it doesn’t make sense to devote significant dollars to a state that is creating unreasonable roadblocks for wind development.”

Noe cites the recent suspension of PSC 128 by the Wisconsin Joint Committee for Review of Administrative Rules as the most convincing evidence that Wisconsin is not interested in working in good faith with the U.S. wind energy industry. The rule was the culmination of almost two years of work by the Public Service Commission and resulted in some of the most stringent and detailed wind siting rules in the country. Although restrictive, these rules created a workable compromise between the wind industry and a range of stakeholders.

“Our four projects alone represent more than $600 million of capital investment in Wisconsin and more than 400 construction jobs and 40 permanent high-tech jobs. The industry as a whole has the potential to be a multi-bill ion dollar industry for the state. These projects also generate millions in local landowner payments and local government revenues, cash flow that is sorely needed in Wisconsin’s rural communities.” Noe said.

Midwest Wind Energy, LLC is a leading developer of utility-scale wind farms in the Midwest and Great Plains with seven projects totaling 649 megawatts currently in operation. MWE has an additional 5000 megawatts of projects in its development pipeline.

END

Anti-windies try to kill another wind energy project

From a news release posted on National Wind Watch:

A controversial western Wisconsin wind energy project has come under fire and may be stopped by a federal lawsuit which was filed by a citizens group on February 9, 2011, and by decisive action by a new town board that was elected through a successful recall election of the former town board members who had approved the proposed wind energy project last summer.

After taking office following a recall election on February 15, 2011, the newly elected town board members for the Town of Forest, in St. Croix County, Wisconsin, voted to rescind a controversial wind energy development agreement and other approvals that had been granted to a wind developer, in a decisive vote on March 17, 2011. As a result, the project, which was proposed by a private wind energy developer named Emerging Energies, LLC, is now under fire and may be stopped.

The federal lawsuit was filed on February 9, 2011, in the U.S. District Court for the Western District of Wisconsin, by a Western Wisconsin citizens group named Forest Voice, LLC, and several individual citizens, against the Town of Forest, its former town board members, and Emerging Energies, LLC.

Second Wind Developer Forsakes Wisconsin for Greener Pastures

For immediate release:
March 30, 2011
More information
Michael Vickerman
Executive Director
608.255.4044
mvickerman@renewwisconsin.org

Second Wind Developer Forsakes Wisconsin for Greener Pastures

Citing Wisconsin’s inhospitable regulatory climate, Midwest Wind Energy, LLC (MWE), a Chicago-based developer of wind generation installations, became the second developer in two weeks to suspend all wind energy development activity in Wisconsin. Another Chicago-based wind developer, Invenergy, LLC, announced last week that it had canceled a 100-turbine wind project in southern Brown County.

Both announcements come on the heels of a March 1 vote by a legislative panel to suspend a Public Service Commission (PSC) rule establishing standards for local government review of windpower projects. That body, the Joint Committee for the Review of Administrative Rules, voted yesterday to introduce legislation to repeal the wind siting rule (PSC 128) and direct the Commission to promulgate a new rule.

In 2006 MWE proposed erecting a 98 megawatt (MW) prospect in southern Calumet County, north of We Energies’ Blue Sky Green Field installation. Called Stony Brook, MWE’s proposed development was stymied in 2007 and 2008 by a combination of moratoria and arbitrary ordinance changes imposed at the county and township level. In an interesting twist, the Wisconsin Court of Appeals in 2009 invalidated Calumet County’s wind ordinance, after determining that local governments lack the authority to restrict wind energy systems beyond what is allowed in state statutes.

“One wonders if our political leadership appreciates the economic damage being done to Wisconsin when it decided to pull the welcome mat out from under the wind industry,” said Michael Vickerman, executive director of RENEW Wisconsin. ‘The industry’s exodus to greener pastures will cause manufacturing and construction jobs to migrate to states that are friendlier to wind energy. It will be a challenge for Wisconsin businesses that participate in the wind energy supply chain to avoid being caught up in the collateral damage caused by the prevailing climate of inhospitality,” Vickerman said.

MWE’s 98 MW Stony Brook facility represents about a $230 million investment in a locally available source of renewable energy that would generate more than 130 construction jobs, support 10 permanent high-tech jobs, yield an annual flow of nearly $400,000 to host local governments and more than $500,000 to host landowners, as well as create manufacturing and consulting opportunities for a host of Wisconsin businesses.

An early entrant to the Wisconsin wind development scene, MWE secured permits for two mid-sized windpower facilities now operating: Cedar Ridge, a 41-turbine, 68 MW project in Fond du Lac County; and Butler Ridge, as 36-turbine 54 MW facility in Dodge County. Cedar Ridge is owned by Alliant Energy and Butler Ridge is now owned by NextEra Energy Resources.

— END —

RENEW Wisconsin is an independent, nonprofit 501(c)(3) organization that acts as a catalyst to advance a sustainable energy future through public policy and private sector initiatives. More information on RENEW’s Web site at www.renewwisconsin.org.

Jobs and $1.2 million annually lost due to state's hostile regulatory climate sinks Brown County wind project

More information
Michael Vickerman
Executive Director
608.255.4044
mvickerman@renewwisconsin.org

Less than a month after a 10-member legislative committee prevented a statewide wind permitting rule from taking effect, Invenergy, LLC, a Chicago-based wind developer that owns and operates the 86-turbine Forward Energy Center installation south of Fond du Lac, has ended efforts to install 100 turbines in southern Brown County.

In a March 21 letter to the Public Service Commission (PSC), Invenergy singled out the recent suspension of the agency’s wind siting rule as a significant factor in its decision to cancel the Ledge Wind Energy Center. “The absence of regulatory stability has made it imprudent for Invenergy to proceed with investments in a project which unknown regulations might make infeasible to construct,” the letter states. Invenergy’s application to build the 150-megawatt Ledge Wind project was filed in October 2009.

“The regulatory environment for permitting wind energy systems in Wisconsin is deteriorating rapidly,” said Michael Vickerman, executive director of RENEW Wisconsin. “The rollback started with Governor Walker’s proposal to impose onerous and unworkable setback requirements on wind turbines, and continues with the Legislature’s assault on the PSC’s wind siting rule.”

“By all appearances, it seems that Governor Walker and the Legislature intend to close the door on wind development in Wisconsin once We Energies completes its Glacier Hills project later this year,” Vickerman said.

The PSC rule, which was scheduled to take effect March 1st, would have fulfilled the Legislature’s intent to create uniform siting regulations to replace what had become a restrictive and hodgepodge of local requirements. On that very day, the Joint Committee for Review of Administrative Rules suspended the rule on a 5-2 vote that tracked along party line votes (Republicans in favor; Democrats against).

Had the 150 MW Ledge Wind Energy Center gone forward, it would have generated $600,000 annually in municipal revenues to Brown County and four host townships, and more than $600,000 annually to host landowners and their neighbors. On average, installing one turbine requires 1,325 hours of craft labor, and a 100-turbine wind project will support a payroll of over $10 million, according to figures provided by Boldt Construction.

“Invenergy’s cancellation of its Ledge Wind project should not come as a surprise,” Vickerman said. “It should be expected with a political leadership that treats windpower as a pariah energy source. Until the day the Governor and the Legislature put aside their ideological blinders and recognize the benefits that come with developing a clean, locally available and inexhaustible energy source, Wisconsin will remain a very unappetizing place to pursue utility- scale wind projects.”

“Wisconsin can ill-afford to export windpower-related jobs and local payments to other states,” Vickerman said.

— END —