Xcel rethinking biomass project

From a blog post by Tom Content in the Milwaukee Journal Sentinel:

Xcel Energy Corp. is rethinking its plans to build the largest biomass power plant in the Midwest after the projected cost rose by one-third.

The power company, which has a Wisconsin utility based in Eau Claire, was planning to build a biomass gasifier that would replace an existing coal-fired power plant on the shore of Lake Superior in Ashland.

The company initially pegged the project at $58.1 million, but after more work it was determined that it would cost $79.5 million – an increase of nearly 37%.

The company will assess whether to use a different technology to burn wood at the power plant, said Don Reck, Xcel director of regulatory and government affairs.

Costs rose during a more detailed engineering review that concluded more work would be needed to retrofit the coal boiler to gasify biomass than the company and its consultants first concluded.

“We’re looking at all the options that we had included in the application, as well as at least one or two new ones that have surfaced since the application was filed,” Reck said.

The Wisconsin Paper Council and Citizens’ Utility Board expressed concern about the escalating price tag.

“This project was sort of a mixed bag for us,” said Charlie Higley, executive director of the Wisconsin Citizens’ Utility Board. “We want to see alternative projects developed using alternative fuels, but this project definitely raised some concerns regarding costs and feasibility.”

Xcel’s analysis follows a recent meeting of the Public Service Commission at which commissioners expressed concern about the cost of the project and said that in light of the rising price the agency would likely need to take a second look at whether to allow the development to proceed.

The PSC had attached a condition requiring the utility to come back if the cost of the project went above a commission cap of $63.9 million, or 10% higher than the utility’s projection.

Canadian company’s first U.S. turbine spins plenty of power for cranberry farm

From a news release issued by RENEW Wisconsin:

MORE INFORMATION
Ry Thompson
Seventh Generation Energy Systems
608.467.0123
thompson@seventhgenergy.org

Alicia Leinberger
Seventh Generation Energy Systems
608-333-5375
alicia@seventhgenergy.org

Canadian company’s first U.S. turbine spins plenty of power for cranberry farm

Dentist Frederick Prehn, owner of Prehn Cranberry Marsh near Tomah, wanted the power that the cranberry farm paid for without having to pay the utility.

“The second order of business, I wanted a turbine that has a history of working in low wind speed,” said Prehn.

A 35-kilowatt (kW) Canadian turbine, perched on a 140-foot-tall tower, accomplishes both. The first of its model line ever manufactured by Endurance Wind Power, Prehn’s wind generator underwent five months of testing at the company’s Quebec manufacturing facility.

“Wind speeds are all relative,” Prehn said. “The wind speed in the cranberry bog isn’t as good as the Great Lakes, but I’m amazed. I’ve gone through all the data I can gather, and the turbine is producing pretty well.”

“The Endurance fits Wisconsin’s climate conditions,” according to Ry Thompson, a project manager with Seventh Generation Energy, Madison, which installed the turbine.

“We’ve been eager to install one of these,” Thompson said. “It’s a very well-designed, durable machine and the 30-foot long blades make it suitable to lower wind speed environments, as are common in Wisconsin,” Thompson said.

“This should be a very popular turbine among farmers, schools, small municipalities, and manufacturing facilities,” he added.

Canadian company’s first U.S. turbine spins plenty of power for cranberry farm

IMMEDIATE RELEASE
May 24, 2010

MORE INFORMATION
Ry Thompson
Seventh Generation Energy Systems
608.467.0123
thompson@seventhgenergy.org

Alicia Leinberger
Seventh Generation Energy Systems
608-333-5375
alicia@seventhgenergy.org

Canadian company’s first U.S. turbine spins plenty of power for cranberry farm

Dentist Frederick Prehn, owner of Prehn Cranberry Marsh near Tomah, wanted the power that the cranberry farm paid for without having to pay the utility.

“The second order of business, I wanted a turbine that has a history of working in low wind speed,” said Prehn.

A 35-kilowatt (kW) Canadian turbine, perched on a 140-foot-tall tower, accomplishes both. The first of its model line ever manufactured by Endurance Wind Power, Prehn’s wind generator underwent five months of testing at the company’s Quebec manufacturing facility.

“Wind speeds are all relative,” Prehn said. “The wind speed in the cranberry bog isn’t as good as the Great Lakes, but I’m amazed. I’ve gone through all the data I can gather, and the turbine is producing pretty well.”

“The Endurance fits Wisconsin’s climate conditions,” according to Ry Thompson, a project manager with Seventh Generation Energy, Madison, which installed the turbine.

“We’ve been eager to install one of these,” Thompson said. “It’s a very well-designed, durable machine and the 30-foot long blades make it suitable to lower wind speed environments, as are common in Wisconsin,” Thompson said.

“This should be a very popular turbine among farmers, schools, small municipalities, and manufacturing facilities,” he added.

The generator begins to produce electricity when the wind blows just under 8 miles per hour (mph). With an estimated average wind speed of 12.5 mph at his location, Prehn expects to harvest as much as 85,000 kilowatt hours of electricity – more than 150 percent of the amount he needs. The turbine powers a shop, three homes, and two wells. The excess energy is sold to the Oakdale Electric Cooperative, the farm’s local utility.

In addition, Seventh Generation installed a 5 kW solar electric system at the farm. “Some days the turbine produces goose eggs, and the solar system continues to crank out the electricity, and there’s no maintenance,” Prehn said.

“This is a shining example of home-grown energy,” stated Michael Vickerman, executive director of RENEW Wisconsin, a nonprofit advocate for all types of renewable energy.

“Installations like these help reduce Wisconsin’s dependence on coal from Wyoming which is transported here using oil from the Gulf of Mexico,” Vickerman said.

Prehn apparently agrees. He already has a contract with Seventh Generation to install a second Endurance turbine that will be slightly larger than the first.

END

RENEW Wisconsin (http://www.renewwisconsin.org/) is an independent, nonprofit 501(c)(3) organization that acts as a catalyst to advance a sustainable energy future through public policy and private sector initiatives.

State should study impact of biomass plant

From an editorial in the Wausau Daily Herald:

The group of citizens who are working to stop a proposed biomass plant near the Domtar paper mill in Rothschild have been working to cast doubt on virtually all of the claims made about the project — environmental claims, economic claims and so on.

Of their concerns, the questions around the plant’s environmental impact are the most serious, because the air emissions have the potential to do the most harm.

Domtar and We Energies have answered them in some detail, and we have no reason to doubt their analysis of the plant’s impact. Still, there’s no getting around the fact that those companies have an economic incentive to spin the facts in a way that is most beneficial to their project.

That’s why we all would benefit from an environmental impact statement on the project by the state and federal governments. It would provide a solid and independent expert analysis of the project.

The regulations governing these projects are arcane, but the essence of the argument is easy to understand: The state Public Service Commission, sometimes in conjunction with the Department of Natural Resources and federal agencies, has the capacity to prepare an independent assessment of the real environmental effects of the proposed project. This includes the impact of emissions, noise and other factors.

By statute, that analysis is automatically triggered for any power plant generating 100 megawatts or more. The proposed biomass plant will generate 50 megawatts, so an environmental impact statement is not required.

That doesn’t mean it shouldn’t be completed. Fifty megawatts of electricity still is a major power plant. An environmental impact statement would add an important expert perspective to the local discussion about the plant. This is a big project, and a relatively new technology. It bears scrutiny.

Racine Montessori adding solar panels

From an article by in the Racine Journal Times:

RACINE – Workers spent Wednesday installing new solar panels at the Racine Montessori School, the latest move by the school to go green.

The school’s solar panel project has been in the works for about two years and is finally being completed this week with the installation of 84 panels on the roof of the school’s gymnasium, said Rita Lewis, administrator at the Racine Montessori School, 2317 Howe St.

The panels are being installed by Madison-based H&H Solar Energy Services. When installation is complete, the panels should generate about 40 percent of the energy the school needs. To show students when the panels are working, ceiling fans directly tied to the panels will be installed in the school’s hallways. The fans’ blades will rotate on sunny days when the panels are absorbing sunlight to convert to energy, Lewis said.

To mark the panels’ installation, the school’s elementary students had a “Solar Celebration” Wednesday where they spent time outside singing sun-themed songs like “You Are My Sunshine” and cooking s’mores in homemade aluminum foil solar ovens, Lewis said.

The solar panels and installation, which cost about $134,000 altogether, were paid for through two large grants from We Energies and two large donations from local families. Clifton and Gladys Peterson and Charles and Kathryn Heide each donated about $22,000 for the project. Gladys Peterson formerly taught at the school and the Heide family had grandchildren attend, Lewis said.

“They are the two families who really made it happen for us,” she said.

The solar panels are the latest green effort under way at the school, which this week was awarded a school Green Award from the Sierra Club of southeastern Wisconsin, according to Lewis.

Alliant says no more coal plants … for now and no nukes

From an article by Judy Newman in the Wisconsin State Journal:

Alliant Energy is giving up on the idea of building more coal-fired power plants “for the time being,” Alliant chairman, president and chief executive Bill Harvey said Thursday.

In an interview after the Madison utility holding company’s annual shareholders meeting, Harvey said Alliant subsidiary Wisconsin Power & Light will not ask for a new coal-fueled power plant to replace one proposed for Cassville that state regulators rejected in late 2008.

“I think it’s politically … too risky to think about building coal plants until climate legislation gets in place,” Harvey said. “There’s got to be substantial technological improvements before the country returns to building coal plants. That’s certainly true for us,” he said.

Thanks to adequate power available to buy on the electric transmission grid, Harvey said it will likely be two or three years before Alliant proposes building another natural-gas-fired power plant. That could happen sooner, though, if the economy recovers quickly or if climate change rules force the company to abandon its older coal-fired power plants sooner than expected.

As for nuclear power, Harvey said Alliant is not big enough to consider spending up to $10 billion to build a nuclear plant but it might buy part of a new one, if one is built. “We have to consider that. We have to consider all possibilities,” he said.