Catching Wind updates news on Wisconsin wind

Catching Wind, a newsletter from RENEW Wisconsin, includes the following updates on wind in Wisconsin:

Siting rule survives challenge, takes effect
Capping a bitter four-year struggle, the Legislature cleared the path for wind energy development to resume in Wisconsin under clear and consistent rules.

By adjourning without passage of bills restricting wind development, the Legislature allowed a statewide permitting rule developed by the Public Service Commission (PSC) to take effect.

Community wind sweeps into western Wisconsin
Two privately owned utility-scale wind turbines are set to rise this spring near Organic Valley Cooperative’s distribution center in Cashton, home of Wisconsin’s first Community Wind project. Called Cashton Greens, the wind project is a joint venture of LaFarge-based Organic Valley and La Crosse-based Gundersen Lutheran Health System.

St. Croix County Wind Project seeks PSC approval
In a first for the Badger State, western Wisconsin, specifically, St. Croix County will provide the backdrop for a high-profile permitting battle over a utility-scale wind energy project. The 41-turbine project would be located in the towns of Forest and Cylon, about 30 miles northeast of Hudson.

Catching Wind updates Wisconsin wind news

Catching Wind, a newsletter from RENEW Wisconsin, includes the following updates on wind in Wisconsin:

Siting rule survives challenge, takes effect
Capping a bitter four-year struggle, the Legislature cleared the path for wind energy development to resume in Wisconsin under clear and consistent rules.

By adjourning without passage of bills restricting wind development, the Legislature allowed a statewide permitting rule developed by the Public Service Commission (PSC) to take effect.

Community wind sweeps into western Wisconsin
Two privately owned utility-scale wind turbines are set to rise this spring near Organic Valley Cooperative’s distribution center in Cashton, home of Wisconsin’s first Community Wind project. Called Cashton Greens, the wind project is a joint venture of LaFarge-based Organic Valley and La Crosse-based Gundersen Lutheran Health System.

St. Croix County Wind Project seeks PSC approval
In a first for the Badger State, western Wisconsin, specifically, St. Croix County will provide the backdrop for a high-profile permitting battle over a utility-scale wind energy project. The 41-turbine project would be located in the towns of Forest and Cylon, about 30 miles northeast of Hudson.

Catching Wind updates wind news from western Wisconsin

Catching Wind, a newsletter from RENEW Wisconsin, includes the following updates on wind in Wisconsin:

Siting rule survives challenge, takes effect
Capping a bitter four-year struggle, the Legislature cleared the path for wind energy development to resume in Wisconsin under clear and consistent rules.

By adjourning without passage of bills restricting wind development, the Legislature allowed a statewide permitting rule developed by the Public Service Commission (PSC) to take effect.

Community wind sweeps into western Wisconsin
Two privately owned utility-scale wind turbines are set to rise this spring near Organic Valley Cooperative’s distribution center in Cashton, home of Wisconsin’s first Community Wind project. Called Cashton Greens, the wind project is a joint venture of LaFarge-based Organic Valley and La Crosse-based Gundersen Lutheran Health System.

St. Croix County Wind Project seeks PSC approval
In a first for the Badger State, western Wisconsin, specifically, St. Croix County will provide the backdrop for a high-profile permitting battle over a utility-scale wind energy project. The 41-turbine project would be located in the towns of Forest and Cylon, about 30 miles northeast of Hudson.

RENEW Cheers End of Wind Siting Impasse

Immediate release
March 16, 2012

More information
Michael Vickerman
Program and Policy Director
608.255.4044
mvickerman@renewwisconsin.org

RENEW Cheers End of Wind Siting ImpasseImproved Regulatory Climate Will Attract New Projects

Capping a bitter four-year struggle, the Legislature cleared the path for wind energy development to resume in Wisconsin under clear and consistent rules.

By adjourning without passage of bills restricting wind development, the Legislature allowed a statewide permitting rule developed by the Public Service Commission (PSC) to take effect. That rule, which the PSC issued in late 2010 after extensive deliberation and public comment, was suspended by a legislative oversight committee on March 1, 2011.

“During the PSC rule suspension, wind development slowed to a virtual standstill, resulting in the loss of millions of dollars in construction and manufacturing opportunities, as well as a significant revenue hit to landowners and local governments,” said Michael Vickerman, Program and Policy Director of RENEW Wisconsin, a statewide organization advocating for more clean renewable energy.

For 2012, wind energy companies in each of the states surrounding Wisconsin are constructing hundreds of megawatts of new generating capacity, compared with a projected addition of five megawatts here, enough to power only 1,000 houses, according to Vickerman.

“We hope this outcome will end the wind industry’s exodus to greener pastures. As with any other economic sector, the wind industry will flourish in a welcoming environment where the rules of the road are clear and consistently applied. We believe that the long-delayed rule will provide the certainty needed by investors, contractors, local governments, and landowners.”

END

Pierce County wind farm plan still in limbo

From an article by Jeff Holmquist in the Pierce County Herald:

The future of a proposed wind farm project in St. Croix County remains in doubt, even as progress is being made on an application before the Public Service Commission of Wisconsin.

The $250 million Highland Wind Project was first proposed about four years ago, when Emerging Energies of Wisconsin LLC approached the Town of Forest in northeast St. Croix County about its idea to install about 40 wind turbines on various properties. Studies of wind in the area proved that the region is well suited for the generation of wind energy. Average wind speeds in the town are about 16 to 17 mph, which is sufficient to turn a large turbine and thus generate electricity.

Since completion of the study, the company worked quickly to gain the necessary agreements, easements and approvals.

The project came to a screeching halt, however, when some township residents objected to having the large turbines scattered throughout the municipality. Some claimed the turbines posed a health risk, while others didn’t want the rural atmosphere of Forest to be compromised.